Procurement support for the 350MW / 1,400MWH Kilmarnock South BESS project

Everoze acted as technical advisor on behalf of Copenhagen Infrastructure Partners (CIP) for the procurement of BESS and BoP contracts for its 350MW, 4-hour Kilmarnock South battery project, which will be connected to the 400kV SPEN network in southern Scotland. The Project was developed by Noriker Power, who has stayed on as construction project manager and to support the procurement process.

Everoze’s primary role was to provide techno-contractual expertise as necessary to get the project to contract signing under a dual-contracting approach (BESS and BoP). This included:

  • Producing invitation to tender (ITT) materials and evaluating responses
  • Producing employer’s requirements for both BESS and BoP and associated division of responsibility matrices
  • Leading interface workshops
  • Negotiation support, including managing technical drafting and modifications
  • Due diligence of final project for CIP’s investment committee

As with the Coalburn 1, Coalburn 2 and Devilla projects previously, the magic sauce behind much of the success of the project was close, unhindered collaboration between Everoze, CIP, Burges Salmon and Noriker Power during all stages. Despite very challenging timeframes, the team brought the project to financial close across all contracts on yet another very large battery project, demonstrating the experience amassed across these parties.

The project has now signed contracts with CATL, who will provide the batteries, energy management system and power conversion equipment, and H&MV Engineering, who will provide all civils, installation and electrical balance of plant up to the 400kV connection with SPEN.

Hannah Staab, Project CEO at CIP, said of Everoze’s support:  “We appreciated Everoze’s deep technical expertise and pragmatic approach throughout the process. Our ongoing collaboration with Everoze has allowed us to capture lessons learnt from previous projects and mitigate construction and operational risks during the procurement stage.”